![]() Winter 2007
|
This is a "Woodland" Cedar Kit-house sold by Linwood Homes in
Milton, Wa. View Linwood Homes website
It's a 2180 sq ft classic northwest Post and Beam Prow House built on a
southeast facing ridge.
Built into the hill, it has
a daylight basement
Began the site prep
work, Summer of 2001
Construction began Spring of 2002
and continues.
![]() View of Building Site Summer 2001 (Looking Southeast ) |
This will be Dave
and Jan's
"getaway/retirement house"
The lot is situated on a north-south ridge, the first of
the
Cascade Foothills.
![]() Dave installing heat tubes in the floor of the basement slab 2002 |
![]() Lumber Arrives! The Linwood Kit Home arrives by two trucks and three trailers |
![]() First wall goes up |
![]() More walls and the house takes shape |
![]() Setting the main beams |
![]() Starting to look like a house |
![]() Siding going on |
![]() View of the rear of the house |
![]() Deck and roof install |
![]() Great room with fireplace |
![]() Final touches to the deck and railing |
![]() View of lower patio and daylight basement entry |
![]() Installing the septic system |
![]() Backfilling the septic tank 2004 |
![]() Wiring the main power panel |
![]() Backfilling the septic system with the new Dozer |
![]() Insulation in the ceiling. Note the true post and beam construction |
![]() Propane tank and piping |
![]() Heating tubes in the main floor |
![]() Radiant heat control panel |
![]() Drywall going up in the greatroom |
![]() Cedar ceiling complete |
![]() Installing the kitchen cabinets 2005 |
![]() Cabinets in place and final leveling |
![]() Picking out the granite countertops |
![]() Shannon painting the upstairs bath |
![]() Railing installation |
![]() Bookshelf System |
![]() Kitchen cabinets complete |
![]() Another view of kitchen cabinets |
![]() Shannon showing the main floor bath |
![]() Installing the basement ceiling |
![]() Permit is signed off! Three years and 360 days (March 2006) |
![]() Now to move on to the finishing touches. Attaching cement board to the fireplace |
![]() Taking the log chosen for the mantle piece to the sawmill More on the Mantle Log |
![]() Mounting the sawn log Mantle above the fireplace |
![]() River rock fireplace Complete |
![]() Basement Stove installation |
![]() Slate Tile Installation |
![]() Basement 100W Digital Ham Station More... |
![]() Solar Hot Tub Experiment |
![]() Completed Kitchen with Slate Floor |
![]() Moving the hot tub from Brier |
![]() This guy had a crane and just put it where we wanted it. |
![]() Final Resting place for the Hot Tub |
Some more Misc building photos...
![]() Foundation pour |
![]() Basement bath groundwork |
![]() Running power from the power pole |
![]() Meter and temporary outlets |
![]() Dave backfilling around the foundation with the JD dozer |
![]() Steps and 2nd floor deck install |
![]() Wiring the upstairs bath |
![]() Upstairs framing and stairs |
![]() Drywall and greatroom |
Recent Developments
![]() Winter Getaway Foreclosure House! in Maricopa AZ More... |
![]() Security Gate More on the Security Gate |
![]() Private Spring Water System More... |
|
Wifi Network |
1-14-12